PCC Patch 2021 Phase 1 and 2

Project Description:

Each year, the City of Urbandale patches a number of city streets that are in need of repair.  The work is divided into two projects, one in western Urbandale, and one in eastern Urbandale.  Please see below for more details of each phase.

Phase 1 West - Project Status Update - 06/07/2021

The 2021 Patch Project Phase 1 has been awarded to Shekar Engineering.  Shekar is currently working in the Horizons Ridge neighborhood north of Douglas Avenue; this stage will take another week or so, weather permitting.  

Around June 14, Shekar plans to complete the Horizons Ridge work and transition to the Telby Knolls neighborhood west of 156th Street.  This stage will take about a month.

Residents will be notified when work will be starting in their neighborhood.

Phase 1

Phase 1 is in western Urbandale and includes the areas from 147th Street to 160th Street and from Maple Drive to Airline Avenue.  

PCC_Key

Phase 2 East - Status Update - 06/07/2021

The 2021 Patch Project Phase 2 has been awarded to Hill Contracting.  Hill Contracting is continuing work on Holcomb Avenue and beginning patches on 71st Street.  Residents will be notified when work will be nearing their area.

Phase 2

Phase 2 is in eastern Urbandale and includes the Holcomb Avenue, the Hickman Frontage Road, 70th Street, 70th Place, 71st Street, and 72nd Street.

PCC_Key