Urbandale News

Posted on: March 12, 2017

2016 Sidewalk Program Bids Approved

Sidewalk Graphic

As designed, this project would provide for the repair of sidewalks noted in the City's annual inspection program that were not repaired by the property owners.  Approved was the low quote of JDA Construction, in the amount of $29,350.  The low quote is $6,166.00 (17.2%) lower than the project cost opinion of $35,466.  The cost savings can primarily be attributed to lower than anticipated unit costs for the sidewalk concrete removal.  It is anticipated that this project would be completed by September 29, 2017.

Facebook Twitter Google Plus Email